Zafertepe Mah. 533 Sk. No:9/B Yağhaneler, Konak, 35250 İzmir, Turkey • Port of İzmir Export Hub
export@ruzgarcooling.com
TR EN
ENGINEERING GUIDE 6 dk / 6 min

Turnkey Cold Storage Construction Stages & Project Timeline

The 7 engineering milestones from CAD sizing and sub-floor preparation to vacuum dehydration and handover.

Turnkey Cold Storage Construction Stages & Project Timeline

1. Engineering & Civil Sign-off

Thermal sizing, CAD drawings, and floor flatness verification.

2. Insulated Envelope & Door Erection

Vapor-tight joint sealing, camlock fastening, and heated door calibration.

3. Nitrogen-Purged Brazing, Pressure Test & Deep Vacuum

All copper lines are brazed under dry nitrogen purge, pressure-tested for 24h, and evacuated below 500 microns before refrigerant charging.

TECHNICAL FAQ ENGINEERING ANSWERS

Frequently Asked Questions

Why is deep vacuuming below 500 microns critical during commissioning?

Residual moisture freezes at the expansion valve and forms acids in POE compressor oil, causing premature motor winding failure.

FACTORY-DIRECT RFQ İZMİR & GLOBAL EXPORT

Request a Turnkey Cold Storage Engineering Quotation

Share your room dimensions, target temperature, and destination port or city. Our refrigeration engineers respond with detailed heat load calculations, CAD layout, and EXW/FOB/CIF pricing.

Direct Engineering Desk

Phone / WhatsApp: +90 506 689 45 82

E-mail: export@ruzgarcooling.com

HQ & Factory: Zafertepe Mah. 533 Sk. No:9/B Yağhaneler, Konak, 35250 İzmir, Turkey

Technical Quote Request Form

Call: +90 506 689 45 82 WhatsApp